Placentia Pumphouse Upgrades
Rodco Mechanical (2014) Ltd. worked with a local general contractor to complete mechanical and electrical upgrades at Clarkes Pond Pumphouse in the Town of Placentia.
Our worked included the supply and installation of:
- new piping and valves to provide potable water to different areas of the Town
- a new 100hp submersible pump c/w casing in wet well
- Installation and configuration of a new triplex VFD control system c/w SCADA communications
- a new gas chlorination system
- Also included in the work was the installation of two PRV and chlorination stations in the Town